Extraordinary solar stringency will have its victims in Hungary
The recent extraordinary measures have overshadowed a previously clear policy and called into question the strategic objectives, says the open letter. According to the association, these extraordinary measures presented in government decrees will claim victims, both among the population seeking to reduce their utility bills and among Hungarian SMEs, which make up the bulk of the solar sector.
The extremely short deadline does not give investors, such as condominium developers, the opportunity to get their projects approved, because not all projects are at the stage where they can start applications immediately. More time is needed to notify the intention to install solar power plants for investments that have already started. The government decree, published on Wednesday night, gives only two working days to prepare the necessary documentation for the application, if it is available at all.
In the 100% solar subsidy scheme launched last year, residents were encouraged even a few months ago to electrify their heating systems and design small-scale solar power plants for their homes through deferrals and other concessions. At the same time, grid upgrades have not taken place, but the public demand has clearly been boosted by this incentive communication, while the new government decree has raised doubts among users with unexpected speed, they add.
Acceptance of tenders has been delayed so much that, in the meantime, the rise in the euro exchange rate and the disruption to supply chains have meant that contractors are only able to install systems at a loss, under the conditions set out in the tender, and the shortage of stocks has often made it impossible to meet deadlines, the open letter says.
In addition to the government decree, which focuses mainly on small-scale, household-scale installations, other obstacles have hampered solar investments by SMEs and industry in recent years:
- Investments in the small business sector are required to build 30% storage capacity, and grid operator MAVIR has made it mandatory to ensure controllability, which for these investments means an increase in costs that makes them economically unviable and technically opaque.
- Zero capacity was announced for power generators in May, followed by the postponement of new capacity opportunities, and many previously approved power plant projects were administratively made impossible.
The clear result of these measures is that the installation of PV systems, even with battery storage, will not be attractive, according to the statement.
The Hungarian Photovoltaic Industry Association, together with the MANAP Industry Association, has formulated the following requests:
- For small-scale solar systems where the grid and transformer circuit are technically suitable for connection, should be an exception and their feed-in to the grid should not be suspended. Allow for the application and authorisation process to continue after 31 October 2022, to be carried out locally by grid engineers, depending on the grid area, and not to restrict feed-in nationally.
- Increase the maximum amount of subsidies awarded under the fully-subsidised solar tender RRF-6.2.1 from the original gross HUF 485,645/kWp to HUF 600,000/kWp gross. If the original amount remains unchanged, more than 43,000 successful applicants could be at risk of losing their projects. Since the tender was launched there has been a significant price increase in the market for photovoltaic devices, as well as in transport and labour costs, and the forint has also depreciated against key currencies.
- For industrial investments where a 30% storage capacity and aFRR (Automatic Frequency Restoration Reserve) regulation is required, they should be able to request an exception and be given a predictable period of free capacity to complete the investments already started in areas where the capacity of the network still allows. This could save investors who started their projects before the regulation tightening.
- Make grid capacity data public, so it can be seen what the government decree adopted was based on, and make it clear in which areas and how much capacity the network can currently absorb, so that the rate of growth can be transparent and planned.
- The minister should use the option stipulated by the government decree to set a date for lifting the suspension as soon as possible, so that solar companies can plan their basic operations, as they cannot build new power plants until then. If a gradual phase out is also possible, the minister should also provide a timetable by 31 October.