Hungary was reportedly facing a financial correction of HUF 110-130 billion in connection with the so-called ‘asphalt case’, but János Lázár, the minister leading the Prime Minister’s Office, brokered a deal with European Commissioner for Regional Policy Corina Cretu last Thursday, and the ‘penalty’ will eventually be HUF 45-51 bn, Magyar Idők (Hungarian Times) reported on Wednesday. As soon as the technical details are clarified, Brussels may transfer the HUF 500 billion on the invoices it had received within one or one and half month, said Zsigmond Perényi, deputy state secretary for international affairs at the PM’s Office. We believe the news, both the agreement and the degree of the penalty cut, should be treated with a pinch of salt.
Highlights of the press report:
Perényi said last Thursday Hungary was offered a “fair deal" by the European Commission (Corina Cretu paid János Lázár a visit), but he did not mention a specific sum.
Although the government continues to believe that it had not applied discriminative measures during the road building projects, “the correction offer was persuasive" hence a political agreement was reached that the parties will settle their dispute out of court.
He said the EC lowered the degree of the financial correction considerably and offered a range of HUF 45-51 bn instead of HUF 110-130 bn, according to the article.
The paper said that according to an earlier proposal by the EU executive, 25% of the contracted amount would have been deducted but this was successfully talked down to an average of 13%.
The exact figure is not public yet since after the political agreement it needs to be clarified on a technical level which contracts will be the subject to the sanction. The original list still included contracts related to the M4 motorway, but these had already been revoked by the cabinet.
There are also tenders that the EC sanctioned in another case. This means the penalty has been paid and another correction may not be applied by the Commission.
It confirmed that instead of the tenders (and invoices) affected by sanctions new projects will be submitted immediately at the expense of the central state budget therefore the asphalt case will not result in net correction for Hungary.
We believe the report should be treated with a pinch of salt, especially because of the figures mentioned. A HUF 45-51 bn correction would be less than half of the originally planned penalty and 13% is slightly more than half of 25%. This difference may stem from the fact that the exact invoices and their volume and the content of EU funding in these projects will fundamentally determine the overall financial correction that the individual (invoice by invoice) correction will add up to.
Caution is also warranted because Portfolio learned last Thursday that the Commission did not arrive for the meeting with Hungarian authorities with a new offer, i.e. the massive ‘discount’ mentioned by the paper is similar to the penalty reduction the EC had originally offered a few years ago.
In our previous story we estimated the financial correction at around HUF 100 bn, although eliminating the M4 projects and other technical issues (disregarding invoices that had already been subject to correction) may considerably lower this “fine". However, the disputed volume of contracts and the aforementioned 13% average correction would still result in a total financial correction of at least HUF 60-70 bn.
The asphalt case
In July 2015, the European Commission officially suspended funding for Hungarian road construction projects, after examining the so-called asphalt case for 18 months. The EC found fault with a practice Hungary had been applying in road construction tenders since 2007. The Commission launched a probe into those contracts because only those construction companies were allowed to run in tenders for road construction projects co-funded by the EU that had asphalt mixing plants within a 50-kilometer radius of the given road stretch or in the county where the road was to be built. Barring other potential bidders from the tenders this way constitutes an infringement of EU competition regulations.
Importantly, the paper noted that
the government will revisit the sanctioned tenders a year from now, at the end of the accounting period, and in whichever case it is substantiated that a particular company was at fault it will be obliged to repay the subsidy in question.
This means the cabinet will revisit a bill from last summer, according to which the cabinet would pass on the fiscal sanctions by Brussels to the construction companies.
"We have outstanding issues; to the tune of some HUF 600 billion. We are ready to turn to court in the asphalt case and the road construction companies must be clear that if Hungary loses this case we will make them pay for this," Lázár said in December 2015.
What is odd about this is that if the government does want construction companies to “pay for their mistakes" why would it wait a year. Most of the problematic invoices will be brought to light anyhow as a result of the ongoing technical consultations.
Charting is displayed using TradingView's technology, a platform, where you can build advanced charts,