Economy
Hungary found to have misused EUR 283 mln in EU metro funding
The European anti-fraud office, OLAF, uncovered “serious irregularities — fraud and possible corruption" in financing for the €1.7 billion project, according to the report. It recommended that the European Commission department responsible for regional and urban policy reclaim EUR 228 million and that the European Investment Bank be repaid EUR 55 million.
“OLAF can confirm that it has concluded an investigation into alleged fraud and irregularities related to the development of Metro Line 4 in Budapest, Hungary," a spokesperson for the anti-fraud investigator said.
The European Commission’s regional policy department had earmarked EUR 696 million for the project, but earlier audits had resulted in some EUR 322 million being reallocated from the metro to other projects in Hungary. Fiscal corrections in EU project financing are not uncommon, and funding is usually deployed on other projects within a country.
OLAF has also submitted judicial recommendations on the case to Hungarian and British authorities. The Commission has received OLAF’s findings and is assessing its options, according to European Commission spokesman Jakub Adamowicz. The EIB said it is considering how to respond to the recommendations from OLAF, and that in the past it has requested repayment of loans when corruption has been uncovered.
Hungary’s deputy state secretary for transport issues, Flórián Szalóki, said the authorities in Budapest had received a hard copy of OLAF’s 104-page report but warned that it would take months before any decision on money being repaid was taken.
“OLAF can confirm that it has concluded an investigation into alleged fraud and irregularities related to the development of Metro Line 4 in Budapest, Hungary," a spokesperson for the anti-fraud investigator said.
The European Commission’s regional policy department had earmarked EUR 696 million for the project, but earlier audits had resulted in some EUR 322 million being reallocated from the metro to other projects in Hungary. Fiscal corrections in EU project financing are not uncommon, and funding is usually deployed on other projects within a country.
OLAF has also submitted judicial recommendations on the case to Hungarian and British authorities. The Commission has received OLAF’s findings and is assessing its options, according to European Commission spokesman Jakub Adamowicz. The EIB said it is considering how to respond to the recommendations from OLAF, and that in the past it has requested repayment of loans when corruption has been uncovered.
Hungary’s deputy state secretary for transport issues, Flórián Szalóki, said the authorities in Budapest had received a hard copy of OLAF’s 104-page report but warned that it would take months before any decision on money being repaid was taken.