Hungary is the only one in the EU that wants Russian-built nuclear power plant
The agreement to install a new reactor unit with a nominal net electrical capacity of 1,100 megawatts (MW) represents a significant change from the past, as Bulgaria has relied entirely on Russian nuclear technology and nuclear fuel.
This dependency has also determined Bulgaria's position on the sanctions on Russia's nuclear exports in 2022, which were planned to be imposed in the wake of the attack on Ukraine, and which the Balkan country has thus naturally opposed.
Under the FEED contract signed recently, work is commencing to assess Bulgarian industry and the existing infrastructure at the Kozloduy site for its potential to support the construction of an AP1000 reactor.
The contract was signed in Pennsylvania, in Westinghouse's headquarters, by Westinghouse Senior Vice President for Commercial Operations Elias Gedeon, and Valentin Iliev, CEO of Kozloduy NPP - Newbuild.
American block to be added to Russian NPP
Before the signing of the FEED contract on 14 June, the two parties inked a Memorandum of Understanding in March to initiate planning for the potential deployment of one or more of its AP1000 reactors at Bulgaria's Kozloduy nuclear power plant.
The MoU established a joint working group which will "evaluate regulatory, licensing and design bases to ensure full compliance with applicable regulations as well as a streamlined execution path to enable Bulgaria to achieve its nuclear energy goals".
The Kozloduy NPP has six nuclear power units, two of which (units 5 and 6) operate with VVER-1000 reactors. Units 1 to 4 operate with VVER-440 reactors, similar to the "old" blocks of Hungary's Paks NPP, which the European Commission deemed unfit for modernisation.
VVER stands for Vodo-Vodyanoi Energetichesky Reactor (Water-Water Energetic Reactor).
During the negotiations in preparation for its accession to the EU in 2007, Bulgaria committed to shut down Units 1 and 2 and Units 3 and 4 of the Kozloduy NPP plant by 31 December 2002 and 31 December 2006 respectively, and to decommission them thereafter.
Change in nuclear fuel supply too
Bulgaria is trying to break away from Russia also in the
Westinghouse Electric Company and Kozloduy Nuclear Power Plant (KNPP) have signed a 10-year contract to fabricate and deliver VVER-1000 nuclear fuel for Unit 5. This new agreement guarantees reliable supply of the only fully Western option for VVER nuclear fuel fabrication.
Bulgaria is already seeking to free itself from Russian dependence on nuclear fuel supplies, and in December 2022 signed a 10-year agreement with Westinghouse for the supply of nuclear fuel for Unit 5, starting in 2024. The fuel will be supplied out of Westinghouse’s fabrication site in Västerås, Sweden and is the only fully independent alternative to Russian supply.
Kozloduy is the only nuclear power plant in Bulgaria and the largest in the region. Units 5 and 6 have a total installed capacity of 2 GW and supply about one third of the country's electricity consumption. The units, built in 1987 and 1991, have been upgraded and their operating lifetime extended by 30 years to 2047 and 2051 respectively.
AP-1000 nuclear reactors are currently in operation in the United States and China. Poland has chosen the same technology to develop its nuclear power programme and nine reactors are planned for Ukraine. The technology is also under consideration for several other sites in Central and Eastern Europe, the UK and the U.S., according to a Westinghouse statement.
Paks II is the only NPP to use Russian tech
Although several EU countries had previously planned new capacity expansion projects with Russia's Rosatom,
all but Hungary have backed out by now.
"The war and Russia’s actions in the energy sector will undermine Rosatom’s position in Europe and damage its reputation as a reliable supplier, but its global standing may remain strong," according to an analysis.
Paks IIis the construction of two new blocks, VVER-1200 reactors, with a capacity of 1,200 MW each, in the Paks NPP by Russia's Rosatom in a EUR 12.5 billion project. Under the 2014 interstate agreement (without a tender), the Russian Federation will provide Hungary with a state loan of EUR 10 billion to finance 80% of the Paks II project. The loan’s repayment period is 21 years, while the remaining 20% of the project’s costs are planned to be financed by the Hungarian government.
Earlier this year, there were also rumours that the Hungarian government might replace the Russians in connection with the Paks II project and the supply of domestic nuclear fuel. Foreign Minister Péter Szijjártó then called such speculation a lie, stressing Hungary is not backing out of a its deal with Rosatom. He said that it is in fact Germany blocking the participation of Siemens Energy, which could necessitate Budapest switching to France as the supplier of the control technology for the new Paks blocks, while it was supposed to be delivered by the Franco-German consortium.
In addition to the Paks II project, the procurement of so-called small modular reactors (SMRs) may also be on the agenda from 2029-2030 at the earliest in order to expand the domestic nuclear power generation capacity, Energy Minister Csaba Lantos said in an interview with business daily Világgazdaság.
A long story...
The construction of new nuclear capacity in Bulgaria is a decades-long project with a history of twists and turns that are hard to follow. The Belene project, planned to be the country's second nuclear power plant with a 2,000 MW capacity, was signed in 2006 by the Bulgarian National Electricity Works and Rosatom, but the formal contract was never signed. The project was suspended in 2009, largely for financial reasons.
In 2012, the Bulgarian government decided to build a new unit in Kozloduy. In 2013, the government signed a preliminary agreement with Westinghouse for the development, but a year later, also due to financing problems, negotiations on the planned €7.7 billion investment were broken off. There is no new project cost analysis at the moment.
Then, in 2018, an attempt was made to breathe new life into the Belene project. In 2019, a strategic investor was sought for the construction of the two planned reactor units, and although in 2020, a letter of intent was signed between Rosatom, France's Framatome SAS and the U.S. company General Electric Steam Power to jointly bid, the tender was eventually suspended due to the coronavirus outbreak.
Following the abandonment of the Belene project, it was decided to use the equipment delivered by Rosatom for this project to build the new Kozloduy reactor. In the end, this did not happen, and after the Bulgarian government signed a Memorandum of Understanding with NuScale Power, another US company interested in manufacturing small modular reactors, to expand the capacity of the Kozloduy nuclear power plant.
Then the government signed a Memorandum of Understanding to expand the capacity of the Kozloduy nuclear power plant and has been negotiating with Westinghouse for years to maximise the use of Russian assets, and the Bulgarian Parliament adopted in January 2023 a draft resolution asking ministers to negotiate with the U.S. government to expand the Kozloduy nuclear power plant with a new AP1000 unit.