Last week, Hungarian energy group Mol and Croatia's Janaf conducted several joint tests on the Adria oil pipeline. However, according to Mol's announcement on Wednesday, the latest results do not yet confirm that the pipeline would be capable of transporting sufficient quantities of crude oil from the Adriatic Sea to Hungary and Slovakia in the long term. During the tests, the pipeline was unable to operate at adequate capacity for more than one or two hours at a time.
Mol Dunai Finomító Dufi százhalombatta

Failure in test

Before the test began, the parties agreed to gradually increase the pressure and the number of pumps during delivery. This would achieve maximum delivery capacity, which would then be maintained throughout the test.

"The aim was to examine, in collaboration with our Croatian partner, whether the system could operate stably at maximum capacity over a prolonged period. However, just before the test began, our Croatian partner informed us that

they could only guarantee maximum performance for one hour, after which they would need to reduce the pressure.

According to Mol, this differed significantly from the previously agreed plan, making it difficult to evaluate the test results objectively. After testing had begun, Mol claims that

the Croatian partner company stopped the delivery after just 30 minutes, citing a power supply failure. The system was down for more than an hour.

Further disruptions occurred after the restart, as pressure drops were experienced on the Croatian side during transport. The Croatian side then asked Mol to reduce the pipeline pressure. The Croatian section of the pipeline was subsequently able to operate at low pressure and capacity.

Mol and Janaf have been examining the capacity of the Croatian section of the pipeline for a long time. Several smaller tests were conducted earlier, and in September of this year, a comprehensive testing period involving large volumes of transport began. This will last several months, and the companies will use it to find out how much crude oil the southern pipeline can transport stably and over the long term.

Mol emphasises that the Adria pipeline plays a very important role in supplying Central Europe. However, for it to play a greater role,

it is first necessary to understand the capabilities and condition of the Croatian section of the pipeline, and what is needed to enable it to transport 40,000 tonnes of crude oil per day, 365 days a year.

Hungary could find itself in a difficult position

This development is particularly important given the growing pressure from the European Commission for Hungary

to break free from its reliance on Russian energy.

A few weeks ago, Dan Jörgensen, the European Commissioner for Energy, stated that the European Commission's goal is for EU member states never to purchase Russian energy sources again. More precisely, the aim is to prevent 'even a single molecule' of Russian hydrocarbons from entering the EU. According to Jörgensen, there should be no return to Russian energy sources, even when peace is restored.

Domestic production accounts for around 15–17% of Hungary's annual crude oil consumption. Meanwhile, 86% of imported crude oil originates from Russia. This means that

over 70% of total consumption remains of Russian origin.

This also makes Hungary the largest importer of Russian oil among EU member states. This is largely due to its exemption from EU sanctions, which allows it to continue purchasing Russian crude oil via the Druzhba pipeline.

An EU decision of this magnitude would most likely lead to difficulties in Hungary. This is particularly pertinent given that decoupling from Russian supplies raises two key issues: not only how much it would cost, but also whether it is even possible. This underlines the significance of today's developments.

Opinions of the parties concerned on this matter are divided, to say the least. The most obvious alternative for Mol is the Adria oil pipeline in Croatia, which transports crude oil from the port of Omišalj on the Adriatic coast to Central Europe. However, according to Mol, the situation is not that simple, and the oil company has already highlighted a number of issues.

  • Firstly, if all the countries in the region that are dependent on Russian oil were to rely exclusively on the Adriatic, demand could exceed the pipeline's capacity. This would create another security of supply risk, but this time in the south.
  • Secondly, Mol claims that Croatia's high transit fees could result in significant additional costs. JANAF could justify permanently high fees by citing increased demand and the limited availability of alternative routes, which would further increase the cost of using the Adria pipeline.

However, the current test results provide the strongest indication yet from Mol that

the Croatian oil pipeline alone would probably not be sufficient to supply both Hungary and Slovakia.

The Croatians tell a different story

It is important to note that, although the Janaf pipeline was originally designed to transport 34 million tonnes of crude oil per year, its actual usable capacity is currently 24 million tonnes per year. The system was designed to supply refineries in Croatia, Slovenia, Serbia and Bosnia and Herzegovina, as well as meeting demand in Hungary, the Czech Republic and Slovakia.

Recent tests on the pipeline section between the Sisak terminal and the Hungarian border have shown that this section can achieve an annual capacity of 13-16.4 million tonnes, depending on the number of pumps used.

Most of the domestic refining capacity is linked to two refineries owned by the Mol Group: The Mol Group's Duna (Danube) Refinery in Százhalombatta has an annual processing capacity of around 8 million tonnes of crude oil, while the Bratislava Refinery, which is also part of the Mol Group, has an annual capacity of around 6 million tonnes. Thus, the two refineries have a combined capacity of 14 million tons per year.

The test has confirmed JANAF's readiness to fully ensure, as of tomorrow, the supply of both refineries owned by the MOL Group as well as the guarantees given to the Croatian government and the European Commission,

the company said in April. Thus, if demand from the Czech Republic disappears (as it already has), then, according to the Croatians,

Mol's refineries in Bratislava and Százhalombatta could be supplied up to 100% via the Adria pipeline

with the appropriate infrastructure and technical upgrades. This would enable a significant reduction in Russian imports.

It is important to note that refineries will also need to be converted for this purpose, since they are currently optimised for processing Russian (Ural) crude oil. However, the Százhalombatta refinery is already capable of processing non-Russian crude oil, and Mol is working continuously to increase this capacity. According to the company, the Danube Refinery could be able to process up to 100% alternative oil types by the end of 2026.

Cover photo: Portfolio

 

More in Energy

szászhalombatta-dunai-finomító-mol-olajfinomító-százhalombatta-olajipar-energetika-kőolaj-olaj-üzemanyag-finomító
February 27, 2026 16:17

Friendship outage: Brussels responds to Viktor Orbán's letter and also sends a message to Mol

Debate over Hungarian oil supplies escalates further, reaching political depths

GettyImages-2251563303-volodimir-zelenszkij-Európai-Unió-ukrajna-ukrán-elnök-EU-diplomácia-külpolitika-politika-uniós-csatlakozás-orosz-ukrán-háború
February 26, 2026 09:47

Zelenskyy says Druzhba oil pipeline cannot be repaired "so quickly" despite EU pressure

Viktor Orbán wrote an open letter to the Ukrainian President urging him to "stop his anti-Hungarian policies"

Radoslaw SIkorski lengyel külügyminiszter
February 26, 2026 08:31

Polish Foreign Minister urges EU fact-finding mission to prove Hungarian claim in Ukraine wrong

'We are not close to peace yet' - he says

magyarorszag-ukrajna-europai-unio-zaszlo
February 25, 2026 14:11

European Commission: alternative route can be secured for Hungary's oil supply

The situation caused by the shutdown of the Friendship oil pipeline is becoming increasingly complex

LNG
February 25, 2026 13:30

MET Group inks MOU on LNG with Shell

Deepening their relation further

LATEST NEWS
Charting is displayed using TradingView's technology, a platform, where you can build advanced charts, spot upcoming trends in the stock screener, and find inspiration in multiple trading ideas

Detailed search