In the last days of March, the European Commission's Directorate General for Regional and Urban Policy (DG Regio) sent a very stern letter, setting a deadline of only one month to respond, expressing concerns about the Law LXIX of 2023 on the public construction investment regime, in force since November last year. The EU executive is awaiting more answers from the Ministry of Construction and Transport, which is the author of the law, indicating that failure to resolve matters satisfactorily could result in the suspension of payments from Brussels for operational programmes for infrastructure and construction projects.
The European Commission has called on the Hungarian government to clarify the problems and provide a detailed response, with a deadline of the end of April. EU officials say that, in addition to the possibility of infringement proceedings against Hungary over the legislation,
the possible consequence could be the suspension of payments under some EU programmes.
In simple terms, this would mean that the European Commission would not be able to accept and pay invoices for operational programmes that they consider to be covered by the Construction Act.
This is borne out by the fact that the Commission letter Portfolio has obtained also indicates that
shortcomings in the functioning of the established system for almost all public investments could lead to systemic findings, which could lead to the suspension of payment deadlines and payments or even financial corrections under CPR programmes.
Although the EU letter does not specify which programmes may stop the inclusion of invoices, the Hungarian legislation concerned states that its scope covers "construction projects carried out using funds provided for the Hungarian Village Programme and the Téry Ödön National Tourist House Development Programme in the Hungarian Central Budget Act". It also covers all public works and defence investments that reach the national public procurement threshold.
This may determine how restrictive measures are applied in the future, depending on Brussels' interpretation, and could affect up to €2-6.5 billion of public infrastructure investment through the relevant operational programmes. If it is taken as a breach of horizontal eligibility criteria - which would be a very extreme case - then all EU payments could be affected. The latter is clearly the less likely scenario.
But what are the issues with the law?
The Commission's concerns focus on the extended scope of the law, in particular the provisions on exemptions for certain beneficiaries and projects. In this respect, the text of the law states that the government may, by individual decision, exempt a public works project from the application of the law in order to ensure that the project is carried out quickly "if it is of major national or investment promotion interest or if the project can be carried out with a lower level of central budget resources, taking into account the principle of least cost."
The Commission has stressed the need for exhaustive justification behind these exemptions, underlining the principle of equal treatment of all beneficiaries of EU funds. In addition, questions were raised about the objectivity and transparency of the criteria underlying government decisions to grant certain exemptions, in particular with regard to specific national or investment-promoting interests, as these are not specifically detailed in the paragraphs.
In addition, the selection process for operations eligible for EU support is also seen as problematic. The Commission doubts that the selection criteria in the law are compatible with EU regulations and questions the effectiveness of measures to optimise EU funding for programme purposes. In particular, the parameters for exemptions for certain investments are lacking and concerns have been raised in Brussels about the possibility of discretionary decision-making.
In particular, they have reservations about the coordination of projects with sectoral investment plans and EU-funded annual framework programmes. According to the EU executive, the law does not define the term "EU support" precisely, but uses terms such as "non-direct EU support", "EU support" and "EU co-financed projects", so it is not clear exactly which EU funds and operational support programmes fall within the scope of the law. They ask the government to clarify what is covered by the law and to provide a list of EU-funded operations per programme affected by the law.
The Commission also pointed out in the letter the significant uncertainties surrounding the transfer of ownership, public procurement procedures and the conflict of interest safeguards set out in the law. The law requires the transfer to the Ministry responsible for the project of the ownership of the state-owned and municipally-owned immovable and movable assets necessary for the realisation of the works concerned.
In addition, the exercise of the rights must be transferred to the Ministry free of charge, on the date of conclusion of the agreement, at book value, which must be recorded by the land registry on the title deed and no documents other than those provided by the Ministry may be requested for the execution of the operation.
These included questions on the rationale behind the transfer of ownership at the investment stage, the possible creation of a centralised purchasing body and the adequacy of mechanisms to prevent conflicts of interest in the implementation of EU-funded projects, based on a document obtained by Portfolio.
In the case of conflict of interest, the Commission sees a problem in the fact that a ministry can be both a member of a consortium for a given project and a participant in the preparation of the construction project concerned and in the monitoring committee responsible for supervising its implementation.
Hungary must therefore demonstrate that it has some means of ensuring that conflict of interest rules apply to public procurement procedures involving EU funds.
They also object to the fact that, in their assessment, municipalities that are obliged to transfer property do not have a normal right of appeal against such ministerial decisions.
The implementation challenges and the lack of a transition period for key reforms to the law also require intensive scrutiny, according to the EU executive. The Commission has expressed deep concern about the potential impact of the lack of detailed implementation provisions on the timely implementation of planned investments supported by EU funds.
In addition, the EC is not satisfied with the quality of the decision-making and legislative process: they believe that the impact assessment of the legislation was either not carried out or not thorough. This was despite the Hungarian government's commitment to carry out thorough impact assessments in its recovery and resilience plan.
EU officials explained to Portfolio that they found it problematic that the ministry had only attached a half-page sheet to the draft submitted for public consultation, which only stated that the new procedure would not entail any extra budgetary expenditure or administrative burden. However, according to the Brussels explanatory memorandum, in its Recovery and Resilience Plan Hungary has committed to publish detailed and transparent impact assessments.
Several rounds of correspondence between the government and the Commission on the legislation are expected to continue. There is nothing to stop the parties from negotiating beyond the 30-day deadline now set.
The header of the document also shows that the EU executive had several written consultations with the ministry headed by János Lázár in April, May and July last year, well before the Construction Act came into force in November. This is also indicated in the text by the Commission's reference in places to the fact that they had already expressed their concerns, but "only made a few changes in response to their earlier reservations".
This is reinforced by the fact that the press office of the Ministry of Construction and Transport told Portfolio that, although they had consulted the EU body several times before the adoption of the law,
they had not received any official information on the matter.
The Ministry of Public Administration and Regional Development, which is also one of the recipients, wrote to Portfolio that "the law on the public works order is the responsibility of the Ministry of Construction and Transport".
Portfolio wrote to the European Commission about the letter, but we had not received a reply by the time of publication of this article.